Riverside Public Utilities Riverside City Blue Riverside
::  Water Links
Free Sprinkler Nozzles
:: Evans Reservoir

The work includes demolition of the existing reservoir, and construction of the new 16 million gallons Evans Reservoir, including system connections of large diameter pipelines, water meters, valves, seismic actuated valves, electrical and instrument controls.

Click here to view construction cameras on this project

Construction Updates

Click on the notices below for the latest information about the ongoing Evans Reservoir construction project.

System Connection Schedule - 3/28/11
Alley Work (PDF) - 12/2/10
System Connections (PDF) - 9/13/10
System Connections Map (PDF) - 8/11/10

Project Fact Sheet

  1. Original Reservoir constructed in 1968
  2. Cast-in -Place Reinforced concrete
  3. 16 Million Gallons Capacity
  4. Residents served: 300,000
  5. Estimated Replacement Costs: $20 Million
  6. Reservoir Surface Area: 1.82 Acres
  7. Number of Columns: 168
  8. Overall height of Reservoir: 32 feet
  9. Tons of Concrete: over 13,000

Major Milestones

  1. Notice to Proceed: May 25, 2010
  2. Start Demolition: July 21, 2010
  3. Complete Demolition: September 10, 2010
  4. Work in alley: October 2010 thru March 2011
  5. System Connection "B": March 2011
  6. System Connection "D": March 2011
  7. System Connection "C" & "E" Completed: February 2011
  8. System Connection "F" Completed: July 2010
  9. Substantial Completion: December 17, 2011
  10. Final Completion: March 16, 2012